Project:
Kanawha River Bridge
Interstate 64
West Virginia Division of Highways
Location:
Charleston, WV
Engineer:
T.Y. Lin International
2 Harrison Street
Suite 500
San Francisco, CA 94105
Attn: Kim Prishtina
Attn:
R. Craig Finley, Jr.
Phone: 415-276-0227
General Contractor:
Brayman Construction Corp.
1000 Roebling Way
Saxonburg, PA 16056
Attn: Larry Buchheit, PE
Phone: 304-744-7421
Stay-Form Dealer :
Waco Formworks
940 Jefferson Road
Charleston, WV 25309
Attn: Danny Bragg
Phone: 304-744-4791
|
Type of Bulk Head Application:
The contractor is using Stay-Form to form the bulkheads on this 3000 foot long cast-in-place segmental box girder bridge. Each segment is 16 feet long with an overall height of 40 feet (18 inch thick walls).
|